Ongoing Project

Norview Residence Renovation

This residential remodeling project is progressing through demolition, service updates, expansion work, and finish preparation.

Progress Scrubber

Drag to review remodeling progress

Follow the renovation journey from pre-work assessment through rebuilding, service upgrades, and final readiness.

Frame 1 Norview Residence Renovation progress frame 1
Pre-Renovation State

Existing interiors are being assessed before execution and selective demolition.

1 / 5
Assessment Demolition Rework Services Readiness

Project Details

Status Ongoing
Address Norview Dr, Houston, TX 77022
Estimated Duration 6-8 Weeks
Current Phase Foundation and roofing work are complete, and the team is now installing AC lines while constructing an additional room, attached bathroom, and patio.
Area Covered 1,400 sq. ft.
Enquire About Similar Work

Scope of Work

  • Foundation and structural reinforcement work
  • Complete roofing replacement and installation
  • Installation of AC units and piping lines
  • Construction and finishing of an additional room, bathroom, and patio area
  • Painting, detailing, and fitment installation

Milestone Timeline

  • Weeks 1-2: Foundation work and complete roofing replacement completed.
  • Weeks 3-4: AC line installation and structural preparation for expansion completed.
  • Weeks 5-6: Construction of the additional room, bathroom, and patio completed.
  • Weeks 7-8: AC unit installation, finishing work, and final detailing completed.