Progress Timeline
Chaffin Renovation
Drag the slider to scrub through the complete renovation timeline from start to final handover.
Project Scrubber
Drag to move through the work timeline
This project page behaves like a progress scrubber, where the range slider maps directly to a sequence of real project images from start to completion.
Frame 1
What We Did
- Completed site inspection and planning before demolition started.
- Removed outdated finishes, partitions, and damaged elements.
- Corrected layout flow and carried out civil improvements.
- Installed updated service routing for plumbing and electrical work.
- Completed ceilings, flooring, carpentry, painting, and finishing.
Timeline Breakdown
- Week 1-2: Site check, planning, demolition, and debris removal.
- Week 3-4: Civil corrections and layout work.
- Week 5-6: Plumbing and electrical routing.
- Week 7-10: Flooring, ceiling, and wall preparation.
- Week 11-14: Final finishing, fittings, and project handover.